Tuesday 15th January 2019

Planned Niagara Outage - Niagara Arrêt planifié, scheduled 2 months ago

The SciNet datacentre will undergo a maintenance shutdown on Tuesday January 15 and Wednesday January 16, 2019, starting at 7 am (EST) on the 15th. There will be no access to any of the SciNet systems (Niagara, P7, P8, BGQ, SGC, HPSS, Teach cluster, or the filesystems) during this time.

This is in preparation for the upcoming installation of an emergency power generator and a larger UPS, which will result in increased resilience to power glitches and outages.

The status of the Niagara cluster can be checked on status.computecanada.ca. For up-to-date and more detailed information on the status of all the SciNet systems, you can always check https://docs.scinet.utoronto.ca.

Toutes les ressources de calcul et de stockage situées dans le centre de données de SciNet (Niagara, P7, P8, BGQ, SGC, HPSS, et Teach) ne seront pas disponibles les 15 et 16 janvier, à partir de 7h (heure de l'Est) le mardi 15 janvier 2019.

L’arrêt de service est nécessaire pour installer le nouveau matériel électrique requis pour la prochaine installation d'un générateur de secours et pour augmenter la capacité de l'onduleur (ASI) afin de renforcer la résilience du centre.

Pour connaître l’état de la grappe Niagara, consultez status.calculcanada.ca. Les mises à jour détailées seront postées sur https://docs.scinet.utoronto.ca.